there is one orifice plate already installed on 3" line, but
my previous engineer(who is not working here) removed that
tx, but now i want to take it in to the process, so now what
i have to do now? flow fluid is hytherm oil of temp. 260deg
& pressure is 3bar.

Answer Posted / jigaranadkat

Dear Nitin,

Ideally you shall have all the records, but in case if you do not have the records then try to recalculate the DP value using orifice sizing. You can get data for process condition from your process engineer and B (beta value / bore i.d. from orifice plate itself).

If you do not know how to calculate DP the please forward all the process condition with Line size, Line schedule and B beta value to anadkat.jigar@gmail.com. I can recalculate it for you.

Hope this will help you out.

Best Regards,
Jigar Anadkat
anadkat.jigar@gmail.com

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the Working principle of Dozing valve?

1859


How is automatic reference junction compensation carried out in temperature recorders?

725


What is the GK Value in Flowmeter?

3214


Why is the orifice tab provided?

802


Draw a P& ID showing – orifice flange, plate, dp transmitter, isolation & bypass valves and tubing.

1582






What are different type of instrument cable

1927


A DP transmitter is used to measure the level of an open tank. The drain line of the tank is connected to a control valve, and is configured as, if the level of the tank is 90% the valve should get open 10%. And if the tank level is 10%, the valve should get open 90%. Draw wiring diagram and explain how to configure DP transmitter and control valve using HART communicator. If the span error at output is 1%, what will be the %opening of the control valve at 60% level of the tank?

972


i want to find out iffco get test paper

12423


Explain pH, Conductivity.

1783


hii my name is sujith...i am preparing for HPVL GET 2010... so ,,,pls help me by send any previous questions or material to my site.....(Msujith_12@in.com) thank q

1546


Actual using of tube bender to bend 2 opposite 90 deg at correct measurement center to center of tubing.

1569


how can leve transmetter calibate in feild .and also put cv and flow plz .....

1879


please tell no. & add. of consultancy who recruit me in power plant as instrumen engg. present i m working in power plant as ass.t instrument engg. thanku mahesh 09226562826

1720


what can of fault ofently come in vibration mesurement?

1769


hello friends, can you please send me the model paper or question paper to be prepared for hpcl examinations????????? You can mail me at rahim_here@yahoo.com waiting for your reply........... help me .. plz.....

2230