Method of findingthe dry ingredient quantity of 1 m3
concrete.
Answer Posted / karthiknitw2004
I heard DLBD method is more accurate that using the factor of 1.54 to convert wet volume to dry volume. In DLBD method, To calculate dry ingredients volume in 1:2:4 concrete
Step-1: Calculate Volume of materials required
Density of Cement = 1440 kg/cum (Approx)
Volume of 1 Kg of Cement = 1/1440 = 0.00694 cum
Volume of 01 bag (50 kg) of cement = 50 X 0.00694 = 0.035 cubic meter (cum)
Since we know the ratio of cement to sand (1:2) and cement to aggregate (1:4)
Volume of Sand required would be = 0.035*2 = 0.07 cubic meter (cum)
Volume of Aggregate required would be = 0.035*4 = 0.14 cubic meter (cum)
Step-2: Convert Volume requirement to weights
To convert Sand volume into weight we assume, we need the dry loose bulk density (DLBD). This density for practical purposes has to be determined at site for arriving at the exact quantities. We can also assume the following dry loose bulk densities for calculation.
DLBD of Sand = 1600 kgs/cum
DLBD of Aggregate = 1450 Kgs/Cum
So, Sand required = 0.072*1600 = 115 kgs
and Aggregate required = 0.144*1450 = 209 kgs
Considering water/cement (W/C) ratio of 0.55
We can also arrive at the Water required = 50*0.55 = 27.5 kg
So, One bag of cement (50 Kgs) has to be mixed with 115 kgs of Sand, 209 Kgs of aggregate and 27.5 kgs of water to produce M20 grade concrete.
Cement Sand Aggregate Water
1 bag (50kg) 115 Kgs 209 Kgs 27.5 Kgs
Step-3: Calculate Material requirement for producing 1 cum Concrete
From the above calculation, we have already got the weights of individual ingredients in concrete.
So, the weight of concrete produced with 1 Bag of cement (50 Kgs) =50 kg + 115 kg + 209 kg + 27.5 kg = 401.5 kg ~ 400 kgs
Considering concrete density = 2400 kg/cum,
One bag of cement and other ingredients can produce = 400/2400 = 0.167 Cum of concrete (1:2:4)
01 bag cement yield = 0.167 cum concrete with a proportion of 1:2:4
01 cum of concrete will require
Cement required = 1/0.167 = 5.98 Bags ~ 6 Bags
Sand required = 115/0.167 = 688 Kgs or 14.98 cft
Aggregate required = 209/0.167 = 1251 kgs or 29.96 cft
Procedure Posted on http://www.happho.com/
Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
how to calculate the dry wt of sand and cement for a required design mix?for ex:M20
What is the substitute of Mastic Asphalt?
1.Fe500 and Fe550 having more yield strength than Fe415.But why are we prefering Fe415.? 2. d^2/162 formula for knowing the steel wt/m apply all these three? Thanks.
about higyway engineering
how many monpower required for 1 sqm normal RCC structure ( includes finishes & MEP )
What is the diameter of the 3"inch nails?
How to check slab shuttering level.? Or check list for slab ?
Explain different types of rcc pipes.
at what pressure ply-wood is obtained by gluing wooden sheets
WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.
How many types of slabs are there & how to design it?
how to calculate the crushing strength of cement concrete paver blocks 100x100x60 mm thich.
What is M40 _ TOR - EQ and B.F.S
Why should you show Client/Engineer activities clearly on the project plan?
Hi my name is Binyam and I'm a 7th grader at Mayfield Woods Middle school. I decided to research civil engineering as my career and i need to know a few thing about your profession. What is your daily routine? What are some advantages and things you like about your job? What are some disadvantages What is the hardest thing you have done? What education have you gone through to become a civil engineer? How long is your work day? What is your work environment like? What is your salary? What made you want to become an engineer? What tools do you you use? Thank you for answering my questions