How to calculate the sand and aggregate in concrete
Answer Posted / manzar
For example M15=1:2:4
Sum of ratio=1+2+4=7
Consider volume=2 cu.m wet volume
Dray volume=wet volume+54%wet volume=2+54/100*2=3.08 cubic meter
Cement=3.08*1/7*1440=633.3kg
Sand=3.08*2/7*35.31=31.07 cft
Aggregate=3.08*4/7*35.31=62.14cft
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
Which code is used for tor & tmt steel bar?
IS STEEL BARS IS AS PER ISI TRANSVERSE RIBS SHOULD BE UNIFORM IN DISTANCE, PLEASE EXPLAIN WHY,
What are the reasons for geotechnical site investigations in uganda?
what are the grades of concrete?where and or what purpose a particular grade is used in a particular structure?
What is Grid floor and mention its advantages ?
How many days should curing of plastering, brick work and concrete
What is soil enforcement?
what is cross hair cursor?
What are the advantages of cad?
When was the first motorway built in england?
Why nautical mile is different from statute mile?
how to estimate costing from quantity givin in BOQ and according to this how we fill tender and final rate for perticular work.....?
How much cement and sand are required for 1 square feet of plaster at a thickness of 15 mm at a ratio of 1:4?
any book or article on pumped concrete.
what is smart building materials?