how much quantity of water is required for main wall brick work, partition wall brick work,and for internal and external plastering and how it is calculated?
Answer Posted / vinay
if they give the give w/c ratio then we can calculate water quantity.
for eg if 0.3 is the w/c ratio then,
w/c=0.3
then 1 bag of cement contains 1.25cft so, 0.3*1.25= 0.375cft
1cft contains 28.34 litrs of water then 0.375*28.34=10.625 litres of water is required for 1 bag of cement, generally here for dry volume of concrete is taken as 1 and half times the wet volume i.e 1.54
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
what is grade intersection?
how to caluclate sienerge qty in construction in ap
What happens when,in Prestressed girder the HDPE duct and cone size is provided more than required? (technical answer expected)
What is the Maximum %age of Steel in columns and beams ?
what are the Task work of different labour.?
How do you calculate the power of a centrifugal pump?
a butt weld is specified by
Use of coping on terrace wall and in 4" wall is compulsory or not ?
Civil engineering material testing Standard results
what should be the PCC ratio to construct a plinth of (40x40x4)ft...??also its estimated cost??
how can we calculate steel value, depending on load
For plate load test why we are applying pressure 3 times the proposed allowable bearing pressure? Is there any supporting standards for this?
How is make concrete cube?
Define What is unit weight of normal concrete?
Pls provide me with the calculation or codes related to de- shuttering of flat slabs