how much quantity of water is required for main wall brick work, partition wall brick work,and for internal and external plastering and how it is calculated?
Answer Posted / vinay
if they give the give w/c ratio then we can calculate water quantity.
for eg if 0.3 is the w/c ratio then,
w/c=0.3
then 1 bag of cement contains 1.25cft so, 0.3*1.25= 0.375cft
1cft contains 28.34 litrs of water then 0.375*28.34=10.625 litres of water is required for 1 bag of cement, generally here for dry volume of concrete is taken as 1 and half times the wet volume i.e 1.54
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
could u tell me how to used deform stell bar in reinforce concret?i wanna know the general using in the site!
Describe the sections included in a typical bill of quantities
List out the potential risk factors for workers on the construction site?
225 mm thick RCC slab, how many ton load slab can carry? for example if 33 ton truck loaded with soil, truck having 6 wheels. slab can take load or not? grade of concrete is M35 and slab design Fe500, slab desing one way slab.
Explain what is change order request?
What is the diff b/w ROAD TUNNEL & RAILWAY TUNNEL ??
explain fie benefits of using standard terminology in the measurement process
if we know load bearing capacity of the soil and building load falling in each footing, then how to choose the type of foundation??? and if it is shallow foundation then which type of shallow foundation should be choosen i.e either strip or isolated or raft or combined or cantilever footing???????
what would be the design load of R.C.C Cooling tower per cell.?
I have an plot with area 35*47 = 182.77 sq yards. Out of this iam planning to construct house with 1350 sqfeet each floor .iwanted to build a G+2 house.Need cost estimation for each item
I measured pcc work as 15.34 m cube , the ratio is 1:5:10 ,want to know the cement, sand and metal used for pcc measured as 15.34 m cube at this ratio.
door and window wood work calculations and different methods
what is meant by residual strain?
does a b.tech civil engineer fresher supposed to know how to design rcc structure?
Define absolute co-ordinates?