How to calculate Cement, Sand and Kapachi required for M20,
M25
Answer Posted / kanchan
M20=1:1.5:3,
1cum concrete with water= 1.57cum dry material
For Cement- 1/(1+1.5+3)*1.57=0.285cum=8.55bags
For Sand- 1.5/(1+1.5+3)*1.57=0.43cum
For Aggregate -3/(1+1.5+3)*1.57=0.86cum
M25 -1:1:2
For Cement- 1/(1+1+2)*1.57=0.39cum=11.77bags
For Sand- 1/(1+1+2)*1.57=0.39cum
For Aggregate -2/(1+1+2)*1.57=0.78cum
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
Define What is passive earth pressure ?
I want to know how much the lapping length for the pilecap reinforcement.. we r using single pile cap which is 24mby54m and 2.5m depth.. total 91piles are supporting the pile cap.. how to do a steel reinforcement??
Maximum cement content in 1cum for RCC and PSC? (please give IS,IRC referance?
What is rate for brick masonry work of 1.0 m3 in cm 1:6?
Explain what is 1/8 on the architect ruler denotes?
hoe much fine & sourse agregate required for concrete mix of 1: 1.5:3 by volume in Cu.Ft
why does the most of civil engg is not intersted to going for teaching field?
wat would be the probable interview questions and GD topics for IOCL exam?
Define What is the meaning of a blue land surveyors flag?
What is the difference between engineering stress and true stress?
What is gravity flow?
How about the temperature of grade 35A concrete? Does it depend on the ambient temperature?
Why do you want to work here
it is a corrected question." make a list of engineering property(properties) of soil.
Define line type?