How to calculate Cement, Sand and Kapachi required for M20,
M25
Answer Posted / kanchan
M20=1:1.5:3,
1cum concrete with water= 1.57cum dry material
For Cement- 1/(1+1.5+3)*1.57=0.285cum=8.55bags
For Sand- 1.5/(1+1.5+3)*1.57=0.43cum
For Aggregate -3/(1+1.5+3)*1.57=0.86cum
M25 -1:1:2
For Cement- 1/(1+1+2)*1.57=0.39cum=11.77bags
For Sand- 1/(1+1+2)*1.57=0.39cum
For Aggregate -2/(1+1+2)*1.57=0.78cum
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
Mention different types of roof systems?
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?
What is meaning of tlc
How do we test on design and style in a software?
plumbing CPVC fitting FTE Brass full form
types of survey and levelling instrument ?
For sloping slabs or sloping beams why the tension steel from either side of ridge is taken into compression zone of other side?
How many mortar required for Brickwork of 1 Cu.m works??
relation bet Coefficient consolidation Cv, time factor Tv, drainage path d, & time t is Cv=d2Tv/t Cv=d2t/Tv Cv=tTv/d2 Cv=Tv/td2
Any strength is a stress but any stress is not strength
a solid steel rod length 2m dia and 20mm vertically hangs from celling and has a collar firmly atteched to it. above the collar an annular rubber washer of 40mm th. having stifness k = 5n/mm is placed. determine maximum stress in the rod caused by mass of 5 kg falling through a height of 1.2m.
What are the applications of the modulus of elasticity?
How to arrive d*d/162 , for finding the kg per meter , wt of steel
Explain what is change order request?
Explain what are the skills required to become an architect?