Planning Engineer interview model question and answer
Answer Posted / kumar
should know operation plan, should know outage program,PM & CM schedule,Budget control, Data gathering, create database, documentation, cmms,primavera, ms-office& excel in expertis, 3cs
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What is LB-SR.
how to differentiate between "ALL fuel lost" and "All Fuel Lost" in Boiler MFT condition?
Qatar Fertiliser Company (QAFCO) Shortlisted me for interview (got the intel from my source) for Field Operator- Utilities post. Please let me know what kind of questions they asked? ... this position requires 5 years of experience in Power Plant and background Diploma in Electrical/ Mech. ... my Background is Electrical and I am a sub Assistant Engineer (Operation) at a private HFO based Power plant... PS: Please Let me know what preparation should I take to obtain the Interview which will be take place In Bangladesh soon
im try to calculating seawater flow required for SW-FGD system. I need a guide, equation or method to do it, can some one help me! Thanks very much
what is the trip circuit supervision in an electrical meaning?
How to calculate power press toneage
why is the in steam turbine axial displacement of active side thrust pad is positive and non active side thrust pad is negative.
DCS marshaling Cabinet Power supply can be replace during plant running time? Answer Yes it is possible. I am talking about the controller and cards power supply modules. They are always redundant and connected through diode so that if one power supply fails the other can take the charge immediately.so it is possible to replace one of them in running plant if the other one is healthy. MY question is how switching done.
what is restricted earth fault explain in details
what is the difference between compensated & normal drum level in boiler drum?
operation
procedure of how to generate power in solar plant.
what's the moog valve
How to calculate boiler capacity? I have 1 Autoclave, Which has to use for AAC block. Dimension for this Autoclave is - 13 Meter Length & 2.2 Meter Diameter.
How We Calibrate the vaccum transmitter?