difference between specification and method of statement

Answer Posted / lucy

Specification is the minimum requirement of the project.

e.g.
1. All corridors should not be less than 1.2 meters in width.
2. All ceiling height should be not less than 2.75 meters in height.
3. There should be 1 dedicated parking space for every 10 building occupant.
4. If the corridor is more than 100 meters, there should be a minimum of 3 exit stairs.
5. If a single room have more than 50 occupants, it should have a minimum of 2 exit doors.
6. All internal rooms shall be finish painted.
7. The building Façade should be covered with aluminum cladding.
8. All rooms should have a wooden door.

For specifications, always remember the word : "minimum requirement"

Method statement is the installation method.

You need to describe how are you going to install different items.

e.g.
1. how will you install doors?
2. how will you install windows?
3. how will you install furnitures?
4. how will you install toilet fixtures?
5. how will you install lights?
6. how will you install the foundations?
7. how will you install the tiles?
8. how will you paint the walls?

Is This Answer Correct ?    2 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Explain major differences between routing maintenance and major maintenance.

660


Before casting a basement roof slab which is connected with retaining wall surcharge load (i.e. sand or earth filling) outside the retaining wall is prohibited because of––

1810


Water filter calculation formula

1341


Formula of area of crane hook

1527


what is the quantity of block work required to construct a compound wall of 6" thick,and 212 lenght

970






How to calculate dry of volume of concrete constant?How it comes 1.54 or 1.57

1514


usually hand broken stones are used for cement concrete 1:4:8 in foundation of single /two story houses with a view of economy in construction.what advantages it will give if you use machine crushed stone in place?

1703


In cement making,what is meaning of blend,fineness,density. 

2984


What is the name of this multiplication factors ?

1713


what is the method used for marking of cantilevers in hirise buildings by using theodolite

2436


With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr

1950


Why do you want to work here

1849


I have to design brick column and footing (note: without any reinforcement). Can somebody post me the design or suggest a book where i could possibly find the design? Plz help very urgent

1786


Material calculation of cm 1:6 for 1sqm

1509


How you read 5x3x1 #4 @ 20" 0/C in steel structure?

1076