1:6 ratio, 12mm thickness plastering,
=1/6*1440 *0.012
=2.880 /50kg
=0.058 for 1msq plaster cement,
=100 Sq * 0.058
=5.76 bags for 100 Sqm area
Wastage = 25 %
So 7.2bags
| Is This Answer Correct ? | 11 Yes | 5 No |
Post New Answer View All Answers
why top layer of block work shoud be full size if any cut block adjustable than another layer?
Define What is passive earth pressure ?
3. A vane 12.5 cm long, 8.8 cm dia was pressed into a soft clay at the bottom of borehole. Torque was applied and the value at failure was 55 N-m. find the shear strength of the clay on a horizontal plane.
what is civil engineer greatest strength and weakness?
How you can use different dimension tools in cad? What are the different dimensions available?
How do we test on design and style in a software?
what will happen if one could not properly follow the spacing of slab reinforcement bar?
what"s the sort of beams?
What is the difference in painting using Roller and Brush? What is the paint consumption difference? As per IS one coat of painting is painting from left to right and top to bottom whether this can be done using roller ( Roller Stick height and feasibility) ?
will fix foundation bolts at site with out template is there any procedure?
Hi my name is Binyam and I'm a 7th grader at Mayfield Woods Middle school. I decided to research civil engineering as my career and i need to know a few thing about your profession. What is your daily routine? What are some advantages and things you like about your job? What are some disadvantages What is the hardest thing you have done? What education have you gone through to become a civil engineer? How long is your work day? What is your work environment like? What is your salary? What made you want to become an engineer? What tools do you you use? Thank you for answering my questions
How can we calculate 8- storied Madrasha Building pile capacity by taking SPT value at site?
What are the phases inspections are done by local authority while construction?
Is there the dry coefficient of cement is constant?
Will water damage concrete?