1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement
Required? Brick Size 9" 4.5" 3"
Answer Posted / sulaiman
volume of 1 brick = 0.2286*0.1143*0.0762= 0.00199103 cum
consider 1" thick mortar on either sides
volume of 1 brick with mortar = 0.2413*0.127*0.0889= 0.00272435 cum
No of brick work for 1 cum with mortar = 1/0.00272435 = 367 bricks
No of bricks without mortar for 1 cum= 1/0.00199103 =503 bricks
volume of mortar = (0.00272435-0.00199103)*367= 0.269 cum
volume of mortar in dry condition= 0.269*1.33= 0.358 cum
Cement required= 0.358*1/7*1440= 73.64 kg= 1.473 bags
sand required= 0.358*6/7*35.3357= 10.84 cuft
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
What are the alternate material for steel, Sand and aggregate
in staad ,why we realease a moment of a member ? what is affect if we realease a moment
what are the Task work of different labour.?
how many kg cement & fine sand reqird in one sq meter 1:6 mortar ratio?
Explain what is 1/8 on the architect ruler denotes?
Explain the water bound macadam roag
How to calculate paint drums per meter square
Please tell me Detail cost of providing& laying nominal mix design 1:2.5:5,40mm nominal size.curing complete e/c cost of form work in foundation and plinth i/c carriage.
What is the difference between one-way slab and two-way slab?
A rock anchor 3 1/2” in diameter is placed in rock. The which has an allowable shear strength of 1200 psi. Determine the required anchorage length to safely carry a 80 ton load using a 2.0:1 F.S
When was the first motorway built in england?
how to calculate cost of raw materials of a building for 1000 sqft & also consolidated cost of labour in a 1000 sqft building
strength vs shape factor
The mixture of different ingredients of cement is burnt at?
what is the steel difference between np-2 and np-3 pipes and weight also