1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement
Required? Brick Size 9" 4.5" 3"
Answer Posted / sulaiman
volume of 1 brick = 0.2286*0.1143*0.0762= 0.00199103 cum
consider 1" thick mortar on either sides
volume of 1 brick with mortar = 0.2413*0.127*0.0889= 0.00272435 cum
No of brick work for 1 cum with mortar = 1/0.00272435 = 367 bricks
No of bricks without mortar for 1 cum= 1/0.00199103 =503 bricks
volume of mortar = (0.00272435-0.00199103)*367= 0.269 cum
volume of mortar in dry condition= 0.269*1.33= 0.358 cum
Cement required= 0.358*1/7*1440= 73.64 kg= 1.473 bags
sand required= 0.358*6/7*35.3357= 10.84 cuft
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
How to calculate the force on a column of three story building. What should be the base concrete height?.
1.How much batten required for 1 sqm Shuttering. 2.how much pipe & clamps required for staging of 100 sqm shuttering at 5.0 m height.
Why the statue of liberty is made of copper?
Questions related to civil.engg in company
Anyone have sample questions for bhel interview.please send me as Iam appearing for the interview on 19th sep2008. Kindly send this to my e-mail: arun_prasath_n@yahoo.co.in
What are the basic use of runners and standards of pipelines?
how we check the thickness and line of ceiling plaster.
An interior designer designed a rack with the given dimensions. The dimensions are in feet. This coplanar frame repeats at every 5feet and constitute a space frame. The total length is 120feet. Which steel member will you suggest? A square bar, A square tube or a circular tube. Explain.
what is column foundation
How to calculate or what is the process of calculation for making 1Metre squre area by AAC Blok which quantity of Cement, Sand & Chips are to be required?
in plate load test what is the thickness of plate 20mm 5mm 50mm none
How is calculate the cube molt
With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr
What is the frequency of sampling for the materials of cement,Fine aggregate, Coarse aggregate .and refer which code
how to calculate load bearing column