Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to calculate the cement, sand quantity for plastering?
(10'x10')10mm thick ratio 1:5. wht"s the formula?

Answer Posted / rustam sahu

Suppose we have a room size of 10 ft. x 10 ft. where height of room is 11 feets and width of plastering is 1/2 inch.
1/2 inch = 1/2 divided by 12 = 0.04167 feet
now, let us find out the wet volume for plastering just for one side of wall..
i.e., (length x width x height ) =
= 10 x 0.04167 x 11
= 4.583 c.ft.
for dry volume, segregation value 1.52
Dry volume = wet vol. x seg. value
= 4.583 x 1.52
= 6.97 c.ft.
also, plastering ratio (1:6) sum of ratio = 1+6= 7
per quantity = dry vol. divided by sum of ratio
i.e., = 6.97 / 7 = 0.9957
note: 1 bag cement carries 1.25 c.ft
for cement per bag = 0.9957 /1.25 = 0.7965 bag (for 1 wall)
since a room have 4 walls. so,
0.7965 x 4 = 3.1862 bag
add 10% extra for irregularities at joints or corners
i.e., 3.186 + 0.3186 = 3.5 bags
for sand = per quantity x per ratios x no. of walls
= 0.9957 x 6 x 4
= 23.8968 c.ft

Answer = a room size (10 x 10) ft. having 11 feets height and 1/2 inch width of plastering will required 3.50 bag of cement and 23.89 c.ft. of sand

Is This Answer Correct ?    4 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How do you calculate the power of a centrifugal pump?

1161


Minimum concrete cover in slabs, columns, beams, foundation and other st?

1287


Sir, Iam Applied in rrb for the posts of Junior Engineer.I want to know about the or question previews to study well.Pl send it to shukla_varun1985@yahoo.com.

2174


How to produce the Concrete Grade 30mpa at 12hour? How to prevent for plastic shrinkage crack? How can we produce fire resistant concrete?

1941


what is the use of beam end forces while using a staad ? wha they are show

2977


what is density of 20mm coarse aggregate.plz send answer my below adress e.mail

2148


What is rate for brick masonry work of 1.0 m3 in cm 1:6?

1182


a butt weld is specified by

3050


"Gates of the dams are generally designed of curved shape". Why?

2068


I am a civil engineering student and going to attend interview in this week in an IT company.Will they ask me questions about my area of interest or cs

2560


Who designed the city of washington dc?

1288


How much for the BRC lapping in full yield and half yield < and which table to get it ?

2512


density of crush sand & crush stone or grit powder

6797


For removal of formwork of simply supported slab / beam from where to start the deshuttering? ( Max Bending moment of the simply supported beam is in the center hence is it required to start from the supports?)

2067


Providing and casting in situ cement concrete M-25 of trap/granite/quartzite/gneiss metal for rcc, Providing formwork,Curing the concrete and Complete. what is rate per Cum. and what is rate for M-30 Grade Concrete.

3492