Answer Posted / prathab
cement consumption in plastering work
Plastering work
cemnt sand Total
Mortar 1:6 = 1 6 7
Length = 1 m
Height = 1 m
thickness = 12 mm
Toal area = 1 sqm
Total volume = 0.012 cum
Volume of mortar = 0.001714286 cum
The voids of sand we nead 20% extra material = 0.002057143 cum
Now add 20% eetra to cover uneven surface of brick work = 0.002468571 cum
One bag cement = 0.0347 cum
2 Quantity of cement required = 0.071140387 Bag
= 3.55701935 kg SI.NO DESCRIPTION UNIT QUANTITY
1 CEMENT Kg 3.56
3 Quantity of sand required = 0.014811429 cum
2 SAND Cum 0.0148
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What are the examples of mechanisms?
What is screw,centrifugal and rotary type compressors,how it works and what is principle .
How convective heat transfer is effected and on what factors it depends ?
What are the advantages of a centrifugal pump over a reciprocating pump?
whether anyone has VEDANTA written question papers?if so send me soon i've placements in dec 2nd week
general diesel engine we are using 15w 40 oil unfortunatley our oiller mis used the oil hudralic oil refilled when he doing the service which kind proplem coming in future?
"In refrigeration, why during operations is running low pressure at the suction side?"
Which elements increase the corrosion resistance of steel ?
Where is the expansion tank located?
What is coefficient of contraction?
What is the difference between gear motor and a stepper motor? Like i want to use gear motor for its excessive torque to move my robot. Can i use stepper motor instead?
what is Direct control valve ? explain its practical applications?
What is the weight of 1m3 of seawater?
solar cooker based on the principle
what are various part found in vapour absorption machine and its working