Answer Posted / prathab
cement consumption in plastering work
Plastering work
cemnt sand Total
Mortar 1:6 = 1 6 7
Length = 1 m
Height = 1 m
thickness = 12 mm
Toal area = 1 sqm
Total volume = 0.012 cum
Volume of mortar = 0.001714286 cum
The voids of sand we nead 20% extra material = 0.002057143 cum
Now add 20% eetra to cover uneven surface of brick work = 0.002468571 cum
One bag cement = 0.0347 cum
2 Quantity of cement required = 0.071140387 Bag
= 3.55701935 kg SI.NO DESCRIPTION UNIT QUANTITY
1 CEMENT Kg 3.56
3 Quantity of sand required = 0.014811429 cum
2 SAND Cum 0.0148
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
22216 CC bearing
What are considerations taken into account while creating a piston head?
how buoyancy force is realte with convection?
How many litres did 1 cubic meter contains?
How hydrulic power stearin @ lutch works plz explain?
What is the meaning of less pumping in AC
draw p-v dia distingshing naturally aspirated and supercharged engine with reference to pumping loss?
why desuperheater tubes are bend in shape
Why air is not used to run the turbine?
What does green field project mean?
what is the difference between set up of cast iron manufacturing industry and steel manufacturing industry?
Define emissive power [eb].
Draw L.O. system in diesel engine?
How many lubricating holes are there in cylinder?
What is the difference between newtonian and non-newtonian fluids?