12 mm dia not available at site for raft, 10 mm are available at site how to calculate?

Answer Posted / vaideeswaran

T12 = 140 c/c, ( As per Dwg)
T10(site availability) = (Spacing ?)
Unit Weight of T12 = 0.888 , T10 = 0.616.
0.616/0.888 = 0.693% times lower than T12 ,
0.693 x 140 mm = 97.117 , Say = 97 mm c/c.

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

In the design of bridge arguments what considerations should be made to select the orientation of the wing walls?

640


what is derating factor in cable? what does it mean if derating factor is high/low in terms of thermal resistivity of soil?

2109


which method is used in semi-rigid connection design??

1803


Civil engineering material testing Standard results

1870


What is the purpose of Chipping in the heavy foundation?

1001






What is reinforced concrete?

694


Define unit atmospheric pressure? Difference between gauge pressure, absolute pressure?

1689


how many kg of 20mm, 10mm, dust available in one ton stone boulder

1430


What are the materials used in building a gravity dam?

647


How to get MEP technical,instaaltion & testing data for interview?

1612


types of piles detail,

1821


What is oneside mat. And explain 

2105


Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?

1285


How much cements bag (or in KG) required for 1 Sq. M concrete, for M-30 grad concrete as per CPWD and where is thr proof on site

1219


What are the problems one might face while having a Cantilever balcony?

1049