12 mm dia not available at site for raft, 10 mm are available at site how to calculate?
Answer Posted / vaideeswaran
T12 = 140 c/c, ( As per Dwg)
T10(site availability) = (Spacing ?)
Unit Weight of T12 = 0.888 , T10 = 0.616.
0.616/0.888 = 0.693% times lower than T12 ,
0.693 x 140 mm = 97.117 , Say = 97 mm c/c.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
what is the quantity of block work required to construct a compound wall of 6" thick,and 212 lenght
What are the different softwares used for cad?
Can we apply curing compound on ceiling (slab Bottom)
Which IS Code/American Code applied for coupler test of steel
I need model question papers for writing the Dubai municipality exam,for G+1
natucher of concrete &type of concrete?
how many shuttering material required for 1000 sq.m built up area.
How to determine thee cut length for steel reinforcement bars in R.C.C design
Please let me know about answer for my Question as "What is the maximum wastage allowable of HYSD Steel in any Bridge project as per Code and Code reference also ?
I want to know the material required per square foot in rcc roof. i.e. steel: kg/foot, cement/foot etc.
what is castigliano theaorem
How many square meter can a worker/labor demolish a structure per day?
How can explode a block?
What is diversion tunnel in a dam?
hai, kindly send anyone for output workers format details for construction project in foundation to finishing.