plz tell.. how can we find weight(in kg) of 1 cum of m20
mix..? how can we find the ratio of cement sand and
agregate on site i.e if we given some amount of m20 mix
then hw we find the ratio..?
Answer Posted / ganesh
Dear one,
M20=1:1.5:3 Ratio and M15=1:2:4 all the calculation which given above is not as per Standard so pls post the right one because any one of juniors can follow it blindly,
OPC ( Mix ratio of 1:1.5:3 - M20) ORDINARY PORTLAND CEMENT
Volume - 1 + 1.5 + 3 = 5.5
Total volume of ingredients used = 1.57 Since we use volume batching, wet volume of concrete is 1.57 times the dry volume)
Volume of coarse aggregate required "(3/5.5) *1.57 = 0.856 cu.m
=0.856 * 35.314 = 30.24 cu. ft"
Volume of sand required "(1.5/5.5) * 1.57 = 0.428 cu.m
= 0.428 * 35.314 = 15.12 cu.ft"
Volume of cement required "(1/5.5)*1.57 = 0.2854 cu.m
=0.2854 * 1440 = 411 kgs
= (411/50) = 8.22 bags"
| Is This Answer Correct ? | 17 Yes | 1 No |
Post New Answer View All Answers
How do you prepare Material Recovery Statement for deduction from contractors bills?
VAT and CST ? Which benefits for buyer ? Why benefits?
How to produce the Concrete Grade 30mpa at 12hour? How to prevent for plastic shrinkage crack? How can we produce fire resistant concrete?
hi, i am appearing in HPCL(CIVIL ENGG.)exam. plz send me placement paper of this exam if u are having
What is the crank length in the slab?
how to remove the quantity of metal 1 and metal 2 in concrete
in a corner footing of a building, column lies in one corner. in this condition i want to know if the reactive pressure of soil will be uniformly distributed throughout the footing or will be uniformly varying as in the case of eccentrical loading.
What is the minimum size of the particles of silt soil?
If specific gravity of cement is less than 3.15 what is the cause?
How do we determine the specific gravity of a cement?
What is the average density of soil?
why should we use 20mm graded metal only in vrcc?why we shouldnot use 40mm metal?
Concrete cover for slab, column, beam and footing?
Cut Linten (RCC-1:2:4)on 10" wall - what should be the width and hight of cut Linten? Secondly, 1 X 1.6 foot,4" thick window sun/rain shed (Chajja)should consume steel,Cement, sand and Stone chips?
a) Difference between Ghol , Chimney & fly ash bricks b)Floor to floor height is 3m , rise=15cm , tread 20 cm , how to design staircase means steps landing