how to calculate stair case landing slab bottom shuttering
marking,angle of stair case?
top landing length-1250mm
treads length-2700mm(9X300mm)
rise length-1500mm(10X150mm
top landing level +1.5m lvl
bottom level-0.00m lvl
Answer Posted / chandra shekhar upadhyay
Calculation must be needed for stair case shuttring set up,from first landing bed if it is 1200mm - one trade (300x9)-2D(thicknes of slab)+remaning trade(300x8)
| Is This Answer Correct ? | 0 Yes | 2 No |
Post New Answer View All Answers
How many axes do cartesian coordinate system has?
What is capicity of cap lock scffolding stander(vertical member) and ledger of different size?
01. a. Diagram of a slump cone…………… 1 b. Size of Slump Cone…………… 1 c. Volume of a slump cone by av. Dia method…………… 1 d. Volume of a slump cone by av. area method…………… 1 e. Volume of a slump cone by frustrum method …………… 1 f. Angles of slump cone …………… 1 g. Slump measured by slump cone due to…………… 1 h. Slump does not measured by cylinder / cube due to …………… 1 i) ii) i. Slump cone is to be filled in……………………..Layers.
Gidc technical que paper
kindly mail me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates plz send my email id- VMANDAL91@gmail.com
How you can use different dimension tools in cad? What are the different dimensions available?
What are the problems one might face while having a Cantilever balcony?
Define current ucs?
I was once rejected for US visa in early August. But now I'm going again for interview next week. What are the chances that I will faced the same VO????
Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?
at which depth the construction of tunnel is economical from cost and engineering aspect.
Dear Engineers, Can you please advise me the material requirement to construct a room 4 M x 4 M 1. No. of Standard Brick 2. Requirement of Cement Bags 3. And Concrete for Steel, Cement, sand, etc Thanks
how to calculate the steel in 500yard
Scaffolding IS code NO.
what is the use in canals of longitudinal drains and cross drains in lining areas?