Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

why the Steam Turbine(20MW)center line and gear box center line not in same elevation during coupling alignment ?

Answer Posted / dr.atul bansod

Elevation is given for compensation of natural sag of heavy rotors.Steam turbine manufacturer submits a document known as deflection curve for rotors. On that curve '0'point is specified (any bearing) and other bearings ar kept on different elevation with reference to this "0" refereed bearing.

Is This Answer Correct ?    3 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

can u please tell me how to calculate the concrete quantity for a under reamed pile? r=300mm,depth=3m for a cylinder and for bulb l=.750mm,width=.525

1726


why do you consider yourself a suitable candidate for this position

7444


Qatar Fertiliser Company (QAFCO) Shortlisted me for interview (got the intel from my source) for Field Operator- Utilities post. Please let me know what kind of questions they asked? ... this position requires 5 years of experience in Power Plant and background Diploma in Electrical/ Mech. ... my Background is Electrical and I am a sub Assistant Engineer (Operation) at a private HFO based Power plant... PS: Please Let me know what preparation should I take to obtain the Interview which will be take place In Bangladesh soon

2475


DCS marshaling Cabinet Power supply can be replace during plant running time? Answer Yes it is possible. I am talking about the controller and cards power supply modules. They are always redundant and connected through diode so that if one power supply fails the other can take the charge immediately.so it is possible to replace one of them in running plant if the other one is healthy. MY question is how switching done.

996


can dp type level transmitter work in under vaccum condition

1986


what is the difference between compensated & normal drum level in boiler drum?

1797


How We Calibrate the vaccum transmitter?

1966


why is the in steam turbine axial displacement of active side thrust pad is positive and non active side thrust pad is negative.

3246


What is LB-SR.

2996


what is restricted earth fault explain in details

2043


By any way can we increase the B check hours from 300 to 500

2189


We have Demin Closed cooling water system with expansion tank for cooling oil system. Expansion tank having N2 bladder. Whenever N2 bladder bursts out, Closed cooling water circuit pressure drops and make-up happening, eventhough there is no leaks. And how Circuit pressure drops?

1910


what is the meaning of SST300 V56A in SIEMENS turbine

4354


what is the trip circuit supervision in an electrical meaning?

2114


our 125 kva DG does not start in AUTO mode works normally in MANUAL mode please give me a solution.....

1698