how to calculate no. of bricks for 1 cft?
how to calculate cement and sand in cft?
Answer Posted / nadim shaikh
take brickwork as 100 percent then deduct the mortar
for e.g
6 " wall dimension 10' x 10'
10 feet divided by numbers of mortar layer which will be decided by dividing it by brick laying format for stretcher bond it will be
10' / .33 (4 inch = .33[4/12])
=30 numbers + 1 = 31 ( this was for vertical )
now for horizontal
10'/.75 = 13+1 = 14 joints
now
10' x .5 x .08 ( dimesion of mortar laid in horizontal direction) = 0.4 x 31 joints = 12.4 cu.ft
&
10' x .33 x .08 ( dimension of mortar laid in vertical direction) =0.264 x 14 joints = 3.7
add both i.e 12.4 + 3.7 = 16.1 cu.ft
if 10' x 10' x 6" = 50 cu.ft is 100 % the how much percent will be 16.1 of 50 cu.ft ..
16.1/50x100 = 32.2 say 33%
wooah .. that was quite a lecture
| Is This Answer Correct ? | 10 Yes | 2 No |
Post New Answer View All Answers
it is a corrected question." make a list of engineering property(properties) of soil.
what pressure the NP2 class RCC pipe can sustain?
what is called the inverd level of mabhole chamber?
Can anyone tell me the sequence of the activities in a drawing room, kitchen & Toilet including civil work, finishing, electrical & plumbing fittings
why we use for testing of compression strength concrete the size of specimen 150x150x150. why we are not using another dimension like 100x150x100 uneven dimension.
What Reinforcements Are Used In The Process Of Prestressing?
what is constat for brickwork
How we can calculate the cement, sand,bricks , water , quintity in 1:6 Ratio 1 cubic metre b/w and 1:4 Ratio in 1 Squre metre b/w????
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
Explain what is Critical Path Method (C.P.M)?
In the roof of a pumping station explain briefly the components of a waterproofing system?
I want to know the material required per Square foot in rcc roof i.e.Steel ,Cement,
What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.
While calculating the weight of the steel per running meter, the formula used is [(dxd)/162]. Why 162 is used in denominator & how it is derived?
where tie beam is used? what is the pupose? what dimension of tie beam can provided and number and diameter of steel bars to be used between the columns of 1333mm and 1400.