How to calculate the quantity of water in cement mortar eg.
CM 1:3?
Answer Posted / afroz alam
Ratio given, 1:3, it is depending on quantity of cement in kilograms. then we can multiply by the ratio. Such as we know that, 1 bag of cement = 50 kg. Hence, 50*0.6 = 30 ltrs of water
Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
WHAT IS YOUR EXPECTED SALARY?
How to calculate quantity of plum masonry in 1:3:7
why the openings of sieves are square io size?
percentage of metal,clay or soil & water in water bond macadam roads to know the quantities for each in total volume of 11500 cubic meters
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.
What are the steps involved in the concreting process?
What are the joints wants to made in masonry where door opening, arches like etc..
What is the nature of duties & responsibilites senior civil engineer ?what is self confident & satisfaction should be a senior civil engineer?
What is kn measurement?
1.what type of the rock is most suitable for wet mix macadam in construction of road? 2.what is the highest maximum dry density and optimum moisture content can be acheive by using most suitable crush rock?
primary treatment of sewagw consist of removal of floating materials removal of sand & grit removal of organic materials all above
What are the applications of cad?
. Write a C program to perform following functions:- a. Declare one integer variable of all the storage classes. b. Print all the variables without assigning any values in tabular format. a. The tabular format must contain the variable name, type, storage class and printed value on the screen in RED color.
The building has 12 columns of 12x9 in 3 rows of 4 each in a plot of 50'x30', The central row is strengthened with 16mm twisted rods. The roof area is 1500 sft including balconies. calculate the load factor per sft. Also indicate the number of roofs the building can withstand.
How long does it take concrete to harden?