1) One mason per day how many cu.m work will do as per list
given a) Brick work,hollow brick work and cc block work and
plastering how many m2 per day 2) one carpenter per day how
many m2 will do as well as scaffolding how many m3
Answer Posted / jarrar siddique
1. Brick work in cement mortar in foundation and plinth 1.25cum (45cuft)per mason/day, or 600 Bricks/day minimum.
2. 12mm (1/2) plastering with cement mortar 8.00sqm (80sqft)per mason/day.
3. Supplying, fitting, fixing and removing shuttering & staging 7sqm/carpentar/day.
| Is This Answer Correct ? | 78 Yes | 8 No |
Post New Answer View All Answers
Spider cracks occur in beam bottom due to––
calculate the quantity of cement ,sand,bars and aggregate used for 28*4 ft with 4 inch (125mm) thick
How many feet are in 4 square yards?
Elaborate advantages & disadvantages of using crusher dust instead of sand in rcc work.
Which prize is the alternative to the NOVEL Prize?
what is meant by csr in foundation? what is sbc?what is meant by contour line?
What is the use of offset command?
What is Joule Brayton Cycle?
Gave a cantilever beam with 3 legs.Told to draw the bending moment diagrams, axial force diagrams and shear force diagrams.From BMD he asked to show how the reinforcement will be provided on the tension side.
How to find CN by using arcgis 9.3?
Scaffolding IS code NO.
I have to design brick column and footing (note: without any reinforcement). Can somebody post me the design or suggest a book where i could possibly find the design? Plz help very urgent
Define What is Civil Engineering?
How you can turn off the display for dimension in CAD?
how to clculate the %of concrete strenght achive after curing?load