1) One mason per day how many cu.m work will do as per list
given a) Brick work,hollow brick work and cc block work and
plastering how many m2 per day 2) one carpenter per day how
many m2 will do as well as scaffolding how many m3

Answer Posted / jarrar siddique

1. Brick work in cement mortar in foundation and plinth 1.25cum (45cuft)per mason/day, or 600 Bricks/day minimum.

2. 12mm (1/2) plastering with cement mortar 8.00sqm (80sqft)per mason/day.

3. Supplying, fitting, fixing and removing shuttering & staging 7sqm/carpentar/day.

Is This Answer Correct ?    77 Yes 8 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the material consumption- cement,sand,tiles etc for Toilet dado?

7055


How to hide dimensions in autocad?

641


what is the breaking strength of wall tiles

1948


what are the challenges of being a team leader and a supervisor?

3344


Labor requirement for each item needed? Lean Concrete 103.550m3 Concrete for Foundation and Structure 1753.000m3 Expansion joint 288.000m Contraction joint 127.000m Dowel bar 450.000m

1295






calculate the quantity of water for 1:6 cement mortar

1651


Define What is the tensile strength of wood?

679


What is the tensile strength of marble?

654


How many axes do cartesian coordinate system has?

662


Can you pl explain the procedure steps of singly and doubly reinforced beams in limit state method

1176


how to calculate Rate of analysis for 100 m3 Any ratio of concrete ? including labour

1097


what else we can add rather than admixture in concrete to reduce the cement quantity?

5326


Whats be the minimum foundation depth of multistoried building as per height of building in individual footing?

1385


what is thumb rule for calculating the size of ISMB required for a particular length of span

2959


what is the percentage of silt in black cotton soil.?

1964