1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement
Required? Brick Size 9" 4.5" 3"
Answer Posted / ashok sharma
Standard brick size in meter=.190*.090*.090 =.00154
add 10 mm mortar for ech sides=(.2*.1*.1)=(.002)
bricks required for 1 m3 =(1/(0.002)=500 nos
mortar required =(.002-.00154)*500=.23
add 10% for wastage = (.23*0.1+.23)=.253m3
add 25% for Dry Volumn = (.253*0.25+.253)=.316m3
Send is =(6/7)=0.857*0.316=0.271 cum = 9.571 cft
cement is =(1/7)=0.143*0.316=0.045*1440= 65 kg
| Is This Answer Correct ? | 0 Yes | 2 No |
Post New Answer View All Answers
what is meant by sustainable developement as far construction field is considered. Give suitable examples to explain the same
Dear sir, i want to NBCC & NTPC previous exam papers email Id : madhu_bingi@yahoo.co.in
Design a built-up column carrying an axial load of 1200 KN. Its length is 8m and it is effectively held in position at both ends and restrained against rotation at one end. Assume yield stress of 250 mpa
What are the applications of the modulus of elasticity?
pls tell estimate for 1 kilometre length random rubble masonry 0.90 metre height 0.600 metre width
What is the tensile strength of wood?
what is civil all interview questions
For Wet Mix Mecadam design what is Optimum moisture content
What is the difference between one-way slab and two-way slab?
CAN WORK WELL UNDER DEAD LINES OR PRESSURE?
the magnitude of the buoyant force can be determine by newtons law of viscosity archimidies principal principles of momemnt none
What is the Systematic Responsibility Site Engineer? Who are the above and under co-oridinating ? What is office & Site co-ordination of Site Engineer?
Any strength is a stress but any stress is not strength
afe or not
Can anyone tell me the sequence of the activities in a drawing room, kitchen & Toilet including civil work, finishing, electrical & plumbing fittings