how can we find a burden of potential transformer? what
does it effects? how can we calculate rated load of it?
Answer Posted / tuktuk
Dear Mr.Raghavendran,
Thank you for your answer, I have the same problem but after reading your answer I still have some concerns.
I am really confused. In this case, we do not know the rated burden of the VT. Now we have to calculate the total burden and then selecte the rated value from IEC standards.
__Ztotal, which you mentioned above, is in Ohm or VA?
__Zsec and Zrelay we can get the value from manufacturer but Zlead, is it calculated by this formula: Zlead= (p*L)/S
(where: p is specific resistivity of copper in ohm.mm^2/m; L is length of lead between the PT secondary and the relay in meter; S is the section of lead in sqmm)? Is this true?
__I dont know how can we get secondary current Isec? (I guess Isec=Usec/Zt, isn't it?)
__And Burden in VA = Zt*Isec. As Ohm law, we have P=VI=RI^2=U^2/R, I do not understand the formula that you used to calculate Burden of VT in VA
Hope that you could help me to solve this stuck in my head.
Thank you.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
where can i get vijaya electricals limited in hyderabad interview auestions can u give me the website address plz
Which level of the Transformer oil got dielectric strengh? And why?
3ph motor running with unequal kw and different pf what are the reasons
explain Density
What are the various types of BUSBAR Schemes? explain each
why the name trunking bus PT
what is the function of capacitor duty contactor in an capacitor panel???
why the neutral point in connnection oscillates?
Is any AC drive(VFD) had a feature of DC injection braking? if available please mention the detail. i.e drive can supply braking torque when the motor in idle state.
Starting current of a 10 HP induction Motor is ______ time’s full load current.
if an insulated power and control cables of a running gas diesel gensets laid direct in an open trench i.e, trench bed is not rcc of a power house in which rain water, spillage water alwas exists and all power control cables remains submerged even when gas gensets of 480 kw each runningin on load. These power &control cables runs from power house to switchgear room through these trenches in which water remains most of the time. pl explain its merit & de-merit
What is the maximum operating temperature for a thermoplastic insulated cable?
what is the IPC ? & what the uses ?
difference between Ac and Dc mcb ????
what is the terminal voltage of dc series generator running at rated speed at no load?