200mm*200mm thick block work 1sqm how many cement bags
Answer Posted / sr sharma
0.08512 bag required for 200mm thick 1 sqm block work by 1:4 cement mortar
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What is a kip?
what could be the production cost of 1 cum of concrete by CP30 plant
how to calculate testing date
Required amount of Steel bars, cement/ square feet for roofing of residential building upto 3rd floor.
Permissible wastage of cement as per IS code ? In which IS code I get it?
Can rice husk ash be used instead of coal fly ash for manufacture of clc/ foam concrete
Why is concrete cube test carried out?
What is the strength of cement?
How to calculate thickness of MAT slab & Reinforcement? The dimention of under ground water reservoir is 80'X14'X 12 ft
What are the different methods for drawing an arc?
What is the difference between EPC,DBOOT and BOOT.
What is the difference between absorption & adsorption and sorption?
Who built the sears tower?
How can calculate the requirement of steel bars of rcc slab for 1100 sq ft?
importance of the soundness test to determine the quality of cement use for any construction