1) One mason per day how many cu.m work will do as per list
given a) Brick work,hollow brick work and cc block work and
plastering how many m2 per day 2) one carpenter per day how
many m2 will do as well as scaffolding how many m3
Answer Posted / vijay kumar mukhiya
80 blocks can done by a mason in a day with 1 helper and 10m2 plaster work done by a mason with 1 helper
| Is This Answer Correct ? | 73 Yes | 14 No |
Post New Answer View All Answers
Maximum cement content in 1cum for RCC and PSC? (please give IS,IRC referance?
HOW TO CLACULATE CEMENT AND SAND CONSUMPTION FOR THE STAIRCASE KOTA FLOORING IN THE RATIO OF 1:4 50 MM THICKNESS
"how can we find the approximate quantity of materials using in a building or total Expenditure in percentage for rough estimate after known the construction area(sqm)".please if you know something about that please post the answer.
why are you joining in this (applied post) job and your aim for this job
i) Distinguish between Theodolite and dumpy Level? (Marks-8) ii)Distinguish between Viscous and Turbulent flow? (Marks-8) iii) Distinguish between nominal and design mix? iv) What is standard sand? v) Explain the term plane stress? Vi) Differentiate between principal plane and principal axis? Vii) write short notes on Elastic limit of structural steel? viii) Write short notes on stress concentration? ix) write short notes on "Grading of Sand" ? x) How many grades of concrete are there under standard concrete?
what is features of a typ-ical modern air-conditioning installation?
if dia of slab beam bar is38mm what its clear cover any method of provide clear cover
Why is the statue of liberty made of copper?
estimate quanitity of bricks(19x9x9cm without mortar), cement & sand in 10feet X 10feet wall ?
What is oneside mat. And explain
which are the Indian auther books for STONE COLUMN/GRANULAR PILES?
When was the first motorway built in england?
what is right & short method of measurement of slab&beam
how many minimum admixtures are used in water froofing structures
a) we have 30nos., 300mm dia, 4m length double under reamed piles.calculate excavation quantity.b) tell concrete qty. also.