How to find the requirement of cement and sand for the 1cum of rr masonry work
Answer Posted / s k majumder
First one have to choice grade of Concrete. Say M15 grade for which proportion is 1 : 2:4. total 7
N Now dry volume will be of 1 cum concrete is 1*1.52=1.52 cum
Hence
cement= 1.52/7 = 0.217cum = 7.66cft = 6.12 bag say 6 bag
sand (1,52/7)*2 = 0.434 cum= =15.33cft
Aggregate(=1.52/7)*4 =0.868cum= =30.66cft
Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
how much percent are used 20mm,10mm?
what is the name of shuttering oil used in oman
Explain what is zoning permit?
what is the type of earthing
Hollow block masonry in cement mortar 1:4, 40×20×20cms in superstructure take 10sqm.I want calculation of brick sand
What is the difference between Rock And Murrum. How to claim that excavated material is not a murrum but rock.
1. For 10sq.m area(47 kg bitumen contain) of 45 mm thick bitumen mix layer..how much bitumen is required for 1600 sq.m and how much aggregate need for that ?? 2. And much tonnage of bitumen mix required for 10 sq.m area of 45 mm thick. Please give answer...
how to conversation of all construction material in to brass
sir, please send me the web address of chennai railway to know the online examresults of junior engineer[civil].
how to calculate detail quantity of bricks and mortar for 500 cu.ft masonry work. consider wall thickness 9 inches
How to fix the reinforcement in footing shorter bar at bottom and longer fix at top.
Explain how you can turn off the display for dimension in CAD?
what is the proper procedure in conducting a california bearing ratio penetration test on soil on cbr machine?
Spider cracks occur in beam bottom due to––
what is flashing?