how to prepare Steel schedule or Bar bending schedule.

Answer Posted / nadim shaikh

Bar bending schedule needs manual entry or MS Excel as follows in rows
1. sr. no
2. identification (name of member)
3. shape
4. cutting length (as per required by drawing and RCC consultant
5. total cutting length
6. numbers of members (if identical)
7. Dia of bar
8. per running meter weight of the bar multiplied by total running length
9. 8th point will give total weight of that particular member
10. remarks if any by client or consultant

Is This Answer Correct ?    3 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is the water-cement ratio of mix design while 30mpa in 7 days?

2636


Reinforced concrete: suppose you are doing rough estimate for purchase of rebar for reinforced concrete slab for single stores residential building. You know total concrete volume will be 100 m3. How many tons rebar 6, 10 and 12mm will you require for the project?

2392


How good are the Weinerberger Porotherm bricks that are being used in construction in Chennai, India. Its being used in non load bearing walls and has a compressive strength greater that 35 kg/cm^2 and a density of approx.694 - 783 kg/m3.

2168


though u r a civil engineer, y r u interested in tcs???

2175


What is the difference between Hinged and pinned in Column ends

4788






Exterior Joints,define

1537


How to calculate carrying capacity of the existing water supply trunkmain

1809


1) What is meant by C-soil in geotechnical Engineering? 2) What is Eve board? 3) What will happen when heat is applied to cement? 4) what do you understand by the lateral dimention ?

6113


I have an plot with area 35*47 = 182.77 sq yards. Out of this iam planning to construct house with 1350 sqfeet each floor .iwanted to build a G+2 house.Need cost estimation for each item

1415


Dear sir, i want to NBCC & NTPC previous exam papers email Id : madhu_bingi@yahoo.co.in

2081


what is the procedure involved in preparing mix design of m15 grade as per IS-10262-1982

1668


what are the duties of Site Engineer in work site?

1171


5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)

1663


What is the use of array command?

699


What are the advantages of cad software?

661