I have a single cycle maintenance plan that is triggered by
a counter assigned to a equipment A. If I replace equipment
A with equipment B how do I change my Maintenance plan
counter? When I use IP02 "change maintenance Plan" the
counter box is greyed out. Thanks for any advice.
Answer Posted / mahendra
Create a new counter and plan for equipment b
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What steps must be defined in customizing for alternative labelling?
What is the criteria to change the equipment category?
What is concept of equipment numbering?
what do you mean by reverse counter?
what do you mean by measuring point?
Which task lists are object based?
Which equipment category is used to represent laboratory equipment?
What is the integration between pm and qm in sap?
Is it possible to install an equipment to a functional location without data transfer from function location to equipment?
What action will you take if inspection lot is not generated from calibration order? Which setting will you check?
How can we block service to a customer ? It has to be done through the fl, since most of the equipment belongs to the company and is loaned to the customer ?
If I want to trigger a maintenance order from a maintenance plan on every 7th day of a month, then what settings will I do in the maintenance plan other than a maintenance cycle of 1 month.
Differentiate between control keys pm02 and pm03.
How maintenance strategy plan is different from multiple counter plan.
How pm module is integrated with ehs module?