1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement
Required? Brick Size 9" 4.5" 3"
Answer Posted / ajeet kumar bhatnagar
consider brick joint 10mm.
Brick volume 0.23x0.115x0.76=.0020m3
So for 1m3 brick work brick required=1/.0020=500nos
Now taking joint ,volume =.240x.125x0.086=.00245
Now for 1m3 brick work brick require=1/.00258= 388nos
So mortar volume =500-388=112nos brick=112x0.0020=0.32m3
For 1:6 mortar Cement 1/7x0.320=0.0457m3=0.00457/0.0345=1.32bags=1.32x50=66 kg
Sand=6/7x0.32=.274m3x35.28=9.67cft
| Is This Answer Correct ? | 67 Yes | 14 No |
Post New Answer View All Answers
Permissible wastage of cement as per IS code ? In which IS code I get it?
What year was the keystone power plant in Indiana County constructed?
what is the calculation of raw material for 0.35cum of m-15
In earth work 1300 cum soil how to calculate how many liters require in water
) Design a gussetted base for a column section consisting of one sc 250 with two cover plates 300 x 25 mm carrying an axial load of 2500 KN. The S.B.C. of soil is 250 KN/m2 and the permissible bearing pressure on concrete is 4000 KN.
What is the meaning of Brick- M 35 grade? Is it a common brick or it's a concrete brick?
Pls help me to arrive the rates for centering shuttering for highbay using H-frames?
use ofr concrete as per grade ?
how many running meters in one kilogram of 4mm pvc coated chainlink fencing
SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?
how do you calaculate the total steel quantity of an rcc building using thumb rule?
Can we apply curing compound on ceiling (slab Bottom)
reinforcement slab, beam and column formulas?
Providing ,Cutting, bending and positioning of TMT Bar with cost of binding wire
How do you calculate the power of a centrifugal pump?