Integration of PP with MM , Integration of PP with SD .
Answer Posted / c.kartikeshwar
SAP PP and MM integration is starts with Material Availability check.And also when MRP run for Reorder point( Can be automatic or Manaual).
MRP2 view and MRP 3 view in Material Master the PP and MM integration is mostly linked
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What is time phased Planning?
What is group bom?
What are the customer activities followed for pp module ?
Mention what is the difference between stock transport order and stock transfer order?
What are gaps? Some examples?
Integration between PP and MM Module.
What is processing class, where we do them and why?
Explain Kanban.
What are basic dates?
Explain what is the use of sap material view and list out other parameters where sap material view is applicable?
Both labor and machine categories exist. How would you calculate the process time?
What is meaning of customized reports?
What is MTS and MTO and the difference between them?
Can we use the same routine for materials undergoing the same process/operations? Can we avoid separate routing for each and every material produced?
Why the work scheduling view is required for semi-finished and finished products?