1) One mason per day how many cu.m work will do as per list
given a) Brick work,hollow brick work and cc block work and
plastering how many m2 per day 2) one carpenter per day how
many m2 will do as well as scaffolding how many m3
Answer Posted / yashvant
ready made plaster work one meson can do 12 square meter per 8 hour duty and 2 hour overtime this is enough work as per construction company standard measurement in Dubai.
| Is This Answer Correct ? | 34 Yes | 15 No |
Post New Answer View All Answers
How musch steel i.e. angles, channels,and square pipes are required per square feet for a steel roof of residential two storied building?
How much 1 cum of M15, M20 & M25 concrete weigh?
what is E
Define What materials were used to build the Golden Gate Bridge?
What is braced excavation all about?
How many times we can use Fresh bentonite ford wall execution? Would like to know the clear concept of recycling. After flushing can we use it for another time time for flushing? Or we have to use it for for excavation only?
In cement making,what is meaning of blend,fineness,density.
significance of specific surface area of particles?
is it fair to recruit another prestressing agency once earlier agency has provided guide cone for post stressing the Concrete -I girders? It is observed that the bearing plate of another agency is not matching with the earlier one resulting in protruded strands after stressing from the face of girder. Kindly advice.
Why Is Propping Required For Long Structures Once The Form Work Is Removed?
How to estimate the shuttering material requirement for a slab and beam and shear wall..? Please send thumbrule to estimate material required ( Plywood, Ms plates, runners, acrospans, jacks)
What things architect have to take care of before starting any project?
What is meant by engineering drawing?
At one time what is the height of Lift for concreting for Bridge Piers Class B Loading and refer the code.
Specific gravity of cement?