How much concreat we make by 1 bag cement? (ratio- 1:1.5:3 or 1:2:4)
Answer Posted / virendra kumawat
in M20 Grade(1:1.5:3) concrete make .125 Cubic meter and M15 grade(1:2:4) concrete make .21 Cubic meter.
| Is This Answer Correct ? | 3 Yes | 2 No |
Post New Answer View All Answers
Civil engineering related
We are into industrial flooring (epoxy flooring) business. We buy material from manufacturers.We supply and laying the to companies. In our billing what tax/ taxes to be claimed from companies? Are we applicable for only WCT or any else?
plz.show development and anchorage length in simple diagram.
How to calculate cement, water, fly ash amount for 1 cum if the w/c ratio is 0.4 and fly ash to cement ratio is 1:9
WHAT IS THE CAUSES OF RUTTING ON FLEXIBLE PAVEMENT?
while doing the structural works of a simple ground+1 villa, can the columns be continued immediately after neck columns without tie beam, while the tie beam to be done after columns concreting.
whaat is blister in box girder bridge and what is its function..
what is pouring and explain
how to calculate detail quantity of bricks and mortar for 500 cu.ft masonry work. consider wall thickness 9 inches
Suppose a new brick wall is being constructed,and the courses and not aligned horizontally,what negetives can it cause?
How to calculate Acctually Brickwork Quantity in Honey Comb Brick in circular Soak Pit
what is the relation between pitch of steel and depth of slab?
How foundation is designed, Column design and beam design
How to compute minimum number of columns required for a site from area of site?
Thumb rule for steel qty for 1m2 in kg/m2 column slab footing beam