Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement
Required? Brick Size 9" 4.5" 3"

Answer Posted / ajeet kumr bhatnagar

Actual brick size 230*115*76

So No's of bricks in 1 m3=1÷.23*.115*.076=498nos
Now consider 10mm thick mortar
Now bricks size =240*125*86cm
No's of bricks in 1m3=1/.24*.125*.86=388nos
5% wastge=388+20=418nos actual
Mortar 498-388=110nos bricks
=110*.23*.115*.076=.22m3
30% for dry volume=0.286m3
Wastage 5%=0.015
Net volume=.286+.015=.3(approx)
Cement=.3÷7=0.042=.042÷.0345=1.24 bags

Sand=.042*6=.252m3 or.252*35.28=8.89cft

Is This Answer Correct ?    161 Yes 30 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to estimate the shuttering material requirement for a slab and beam and shear wall..? Please send thumbrule to estimate material required ( Plywood, Ms plates, runners, acrospans, jacks)

2200


why development length = 50D . why not 100D

1997


how will calculate 4"thick solid block quantities 1m3 sand cement ratio and breack up detail

4010


How does siphoning work?

1333


Define What glue is least sticky?

1027


What are the advantages of cad?

1043


I am a civil engineering student and going to attend interview in this week in an IT company.Will they ask me questions about my area of interest or cs

2468


How to calculate the area in squarefeets ?How much area of sqft for this measurements?East 53.3ft West 54ft North 47.7ft South 51.1ft ?

1895


what is the type of earthing

2177


16 questions out of 55 were from the book GUPTA N GUPTA OBJECTIVE of civil engineering. Total ques were 4 ques from hydraullics, 7 from BMC, 4 FROM SOM, 4 from soil mechanics, 6 from transportation, 5 from engineering drawing.

18204


from where ican get sample papers for CET-delhi 2012

2440


How to calculate construction cost of residential building in mumbai

1981


How many axes do cartesian coordinate system has?

1051


in one SQM plaster how much Cement and sand consumed in ratio 1:4

2176


How to find weight of steel in kg if we know the area which is in m2? Following details are known to us, Area=125m² thk of slab=250mm Steel details:T12@200 PS:considering mesh top and bottom with X and Y direction

3038