For 1 cu m of concrete required 1.54 Cu m times dry volume.
Pl give clarification of 1.54 factor
Answer Posted / surajitg
Bulk density of green concrete i.e. mixture of WATER, cement, sand and aggregate is around 1.70 gm/cc or 1700 Kg/ Cum before compaction. So to produce 1 cum of compacted concrete we need 1.54 cum of mix volume including AIR.
| Is This Answer Correct ? | 1 Yes | 2 No |
Post New Answer View All Answers
What is the density of most of construction materials?
need to join coaching institute in coimbatore tamilnadu ......say me the best coaching for IAS
how to calculate reinforcment in staircase cranked beam?
what is flexible and rigid footing?
What is the absolute pressure scale?
What is structural frames or systems?
how many mason and labaur work for a 1 brass bricks plz let me know the calculate & how to made calculation for this and whats the formulas for this?
on what basis the partial factor of safety are decided? form the load combinations
Bitumen grades are 30-40,60-70, 80-100. what is mean by 30- 40
Scaffolding IS code NO.
What is Gsb tollens ?
Explain the Strength of brick?
2. In a container filled with each of the following materials, at a porosity of 40%, determine the upward gradient required to cause the quick condition (a) Lead shot with a G = 13.75; (b) Fibre beads with G = 2.15; (c) Sand with a G = 2.32
what is the venturi effect in buildings? what is green house concept?different types of dams? which dam is economical arch dam or gravity dam. what are the conditions favourible to both of them?
how much tempareture are required to make liquid state of pid leed