Answer Posted / k r kumar ranjan
Normally In Coal based thermal power plant(Either Sub or Super Critical) 60% Bypass is adopted based on condenser heat load calculation keeping 0.9 as Condenser Cleanliness Factor.
If Some designer wants to bypass 100% of generated steam, it is also possible. In fact most Nuclear Steam Turbine adopt same for same reactor shutdown process.
Increase in % capacity of bypass system increases capital cost involved in condenser cooling surface, Extraction pumps, LP Heaters, Pipe Sizing etc.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
what is the basic use of power plant in equipment
operation
What is difference between secondary Air & Tertiary Air and Their use.?
why do you consider yourself a suitable candidate for this position
Which will have more strain energy 1.Spring 2.Circular disc 3.Solid square plate.
what does mean by kva rating
Looking for Bently Nevada surplus 3300/52-01-00-00 Reverse Rotation Monitor , 4 pieces.
can dp type level transmitter work in under vaccum condition
LAPT working in alternator / generator
Why superheated are started before I'd and rd fan?
im try to calculating seawater flow required for SW-FGD system. I need a guide, equation or method to do it, can some one help me! Thanks very much
what is the trip circuit supervision in an electrical meaning?
why is the in steam turbine axial displacement of active side thrust pad is positive and non active side thrust pad is negative.
How to calculate power press toneage
procedure of how to generate power in solar plant.