How to calculate the Qty of Mortar in 1 m3 Brick work? Detailed Calculation Required?
Answer Posted / syed azhar uddin
Size of brick is 10cm x 10cm x20cm
0.1x0.1x0.20=0.002cum.
1/0.002=500 no of bricks in 1 cum.
Cement mortor required for brick work .ratio is (1:5)
1) sand
1 cum=0.20 cum
0.20x actual quantity of brick work
0.20x1=0.20 cum.
2) cement
1 cum =(0.20x1440/5)
To find the value of cementfor 1cum theabove formula is necessary
0.20 refers to 1cum=0.20 of sand.
1440 refers to wt of cement per cum.
Where 5 refers last digit of cement mortor ratio.
1 cum = 57.6 kgs.
No of bags = 57.6/50 kg in one bag
=1.152 bags.
In one 1cum required
Cement: 1.152 bags.
Sand: 0.20 cum.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?
what is the 0 value in quantity surveying
What is change order request?
it is possiblee to produce concrete with out cracks...
What are the advantages and disadvantages of using plastic and timber fenders?
What is semirigid connections?
how will calculate 4"thick solid block quantities 1m3 sand cement ratio and breack up detail
Define the various stages of the project planning process in construction.
What is unit weight of normal concrete?
I need old MMUP exam question and answer for Civil engineering
What are the steps involved in the concreting process?
what is high type road and low type roads
whou haat goals do you have in your career
Sir how to find cutting length for footing steel bars in the shape of "u"
What is meant by dimensioning?