how to calculate required shuttering material like
props,spans,plates ..etc for a slab?
Answer Posted / sahilshah.civil@gmail.com
Props 450 mm C/c
Span near beam 1 nos each & mid span spacing will be 600mm c/c
Plate start from beam end
| Is This Answer Correct ? | 6 Yes | 1 No |
Post New Answer View All Answers
cause of cylinder test failure
What are the causes of building collapse?
Can we use concrete of slump cone in cube casting in which we have already measured slump?
how to decide the mortar ratio 1:4,1:6 in masonry? same in plaster 1:3 and 1:4? which code or any document reference taken to define proportion?
You have 3 snd sample of different FM=0.21,FM=0.95,FM=2.90 which one is suitable for a)plastering on R.C.C b)plastering on masonary wall c)concreting column d)concreting of bored pile.also justify your answer.
Pls help me to arrive the rates for centering shuttering for highbay using H-frames?
what is the water cement ratio for plastering
What is bmc stands for in bmc software?
what are the layers of the national and heir aprox thickness??
how to calculate quantity of bricks in circular manhole with examples.
What are the applications of the modulus of elasticity?
what course did you consider thinking before you enrolled in college?
How to arrive d*d/162 , for finding the kg per meter , wt of steel
In the design of bridge arguments what considerations should be made to select the orientation of the wing walls?
Define What is a kip?