what is right time of slab DE shattering and beam boo tam.
Answer Posted / sahilshah.civil@gmail.com
As per IS 456:2000
a) Columns/vertical member : 16-24 hrs
b) Slab - 3 day - prop to be kept below
c) Beam - 7 day - prop to be kept below
props to slab
a) spanning up to 4.5 m = 7 day
b) spanning over 4.5 m = 14 day
props to beam
a) spanning up to 6 m = 14 days
b) spanning over 6 m = 21 day
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
Specific gravity of cement?
Actually i am confused that how to calculate the bending moment for a semi-circular beam and curved slab.If any one have a good idea about the matter,please give the answer with a suitable example. Thank you......
Describe about the Pile test methods, which are used in Industrial & Multistory Buildings in general.
States some of the commonly used commands in cad software’s?
For plate load test why we are applying pressure 3 times the proposed allowable bearing pressure? Is there any supporting standards for this?
how many shuttering material required for 1000 sq.m built up area.
If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?
what is box type waterproofing and how it is exsiccated and what is the method of doing box type waterproofing
Determine the production capacity of a treatment plant for a city of 1,250,000 population. Assume the specific consumption per capita of 15ol/c/d, non-domestic water use of 30,000,000 m³/year, and UFW of 12%.
What are the advantages and disadvantages of lead products in construction?
Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.
What Reinforcements Are Used In The Process Of Prestressing?
HOW TO CLACULATE CEMENT AND SAND CONSUMPTION FOR THE STAIRCASE KOTA FLOORING IN THE RATIO OF 1:4 50 MM THICKNESS
what is the types of surveying?which type of survey carrying for type of work?
what is the max. and mim. height of vertical post in informatry sign board which is used in highway projects.