If a HV Underground Cable (13.8KV) is layed in the ground below 1.5 Mtrs and any building construction is done on the Cable route. IS this allowable or Not? What should be the clearance. As per ISO construction on HV cable route is safe or Not? Why? Can any body suggest the site for my question?
Answer Posted / ra
cables for 13.8 kv is consider to be medium voltage (not HV ) and if it is routed in cable duct so there is no issue.the purpose of cable duct is to provided safety to cable route.
in case if the cable buried in ground, executor of building construction should notify the client through technical query to solve the issue by technical way according to specification and standard.
in my opinion builder suppose to keep opening for cable routing
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
what is Fault level? why it is calculated? how will u decide same for our plant?
List some examples of renewable energy?
What is the technical difference between On delay timer and a Star delta timer?
WHY EXCITER PHASE SEQUENCE ARE OPPOSITE THAN STATOR SUPPLY PHASE SEQUENCE IN SYNCHRONOUS MOTOR >
What are the conditions for sustained oscillator or what is backhouse criterion?
What is the function of the generator exciter?
Is there any type of starter for DC motor other than two point,Three point and Four point starters?
relation between power station capacity and voltage level?
brief notes on ammeters
What is ST and specify its range of voltage.
Why CBCT rating is 50/1A
Define maximum demand?
What is the principle of HIGH SPEED DIRECT DRIVE MOTOR ?
Why front mounted CT polarities are always towards breaker?
How generating electric power export to grid from the generating station ?