When you received a RA Bill of contractor at HO duly checked
and certified by Site In-charge, How to know at a glance it is
complete in order, do have any one checklist format in this
regard.
Answer Posted / vikas d v
every Ra bill have previous and present amount to be paid if its typical floor or if u know the quantity of items u can easily know
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
Explain the mechanism of cavitations in pipes and drains?
Explain the difference between shear and tensile strength.
i have four storeyed rcc building.basement of the building is around 34 years old.it does not have pillar support.it is having lintel steel support at every 7 feet of construction. how long this building will lost long . can any body help me in this regard
Why Is Propping Required For Long Structures Once The Form Work Is Removed?
In tower foundation, on the time of 3 mtr pit RCC casting if water and mud is their surface of PCC then what will be do?
What are the alternate material for steel, Sand and aggregate
Why M15 is replaced by M20 when ammendment are made in IS456 in 2000?
My daily concrete volume of M25 concrete is 1st day= 25 Cum 2nd Day = 45 Cum 3rd Day = 55 Cum 4th Day = 22 Cum 5th Day =72 Cum 7th Day = 49 Cum. What will be acceptance criteria of concrete considering as per is 456 cl.15 and table 11 (cl 16.1 and 16.3).
How much river sand contain the 6 & 10 wheeler truck? Or Maximum sand that any type of truck carry?
afe or not
residential projects,structural.
hoe much fine & sourse agregate required for concrete mix of 1: 1.5:3 by volume in Cu.Ft
How to calculate the cement and fine aggregate requirement for solid block masonry works in terms of Sqm. 1. 400x200x200mm 2. 400x200x100mm 3. 600x200x100mm 4. 600x200x200mm I need the answer for 1 Sqm of solid block works.
what is pile and deam foundation
150mm bricks size how many use 4.14 m3