I am working in a process industry, in that there are
several sections devided in the SCADA screens and
individual sections may START independently. But sometimes
i am facing problem i.e, if section 2 Stopped by the
operator immediately Section 1 or Section 3 or Section 4 is
getting stopped can you expain the reason behind this?
Answer Posted / jigs
It's possible if all sections are in operational interlock. If you stop one then other will be stopped.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
How to calibrate H2s Dectector
What is motion balance principle?
why orfice is not used for main steam flow calculation
What are primary elements of measuring pressure?
i want to know the interview format fot gail, instrumentation. pls answer me in habib.sami1003@gmail.com
Dear Friends, we are planning to design Power distribution and Fiber optic in the same cabinet.Like Front side Fiber optic and Rear side Power distribution.Is it any possibility of problem occurs like interference etc? Your answer is highly appreciate.
what is the importance of CV in the control valves? how it is calculated?
What is surge and how is it prevented, what is the purpose of bypass valve across AS valve.
In power plant to measure vibration of a turbine we install sensors. Before install this sensor we have to set gap voltage. What is meant by gap voltage and its use?
why we us isolation barrier in hazardous area how it works to protect the area and please clarify its current flow.
Isometric drawings are generated during _________________ phase of a project
List three types Level Switches with their working principles
whatis range of marcury filled tempereture gague
How you calibrate absolute pressure with the calibration range of 0 to 1000 0C Absolute. Please explain the procedure for calibration.
Question on maha cement