Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how we can calculate the quantity of sand & cement & also
Aggregate so give me to this answer for a slab

Length is : 25' /3.28 = 7.62 Mtr
Width is : 30' /3.28 = 9.14 Mtr
Depth is : 0.6"/3.28 = 0.15 2Mtr

Answer Posted / khadar babu

TOTAL VOLUME:
7.62*9.14*.15=10.44cum
(M15 concrete)
cement required= 10.44*6.48=67.7bags=3384.84Kgs

Sand required= 10.44*0.434=4.54cum

Aggregates required= 10.44*0.868=9.06cum

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How many hours should traffic be not allowed after completing wbm road or bst.and min how many hours should road rollers be used.

2199


what could be the production cost of 1 cum of concrete by CP30 plant

1664


What is a hatch patterns?

1050


how much repeitation for conventional and maivan formwork?

1978


What does a construction cost covers and what does not?

1157


What is the difference between built area and super built up area?

1162


What should be the lap length in raft if height of raft is 0.800mm ...it couldn't b 50D or 40D...we just have to join upper and bottom reinforced...is there any formula for determine it...

1920


1m square 20mm plastering how much of water need curing work

1848


How cracks in concrete can be avoided?

1103


how many numbers of 4inch bricks and get consumed in 9 inch BB masonary wall in cubic feet.plz send my below e.mail adress

1799


PL.tell me about civil engineering questions with answer

2480


What are the responsibilities of a construction manager?

1252


how to calculate the rebar depth if forgot the foundation reinforcement (main steel)? is that any calculation or formula we have data sheet of supplier what depth what is the pull out capacity is mensioned in data sheet. if any IS code than its help full to me.

2571


what is the hanekom repairing material after concreting work

2340


What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?

2809