how we can calculate the quantity of sand & cement & also
Aggregate so give me to this answer for a slab
Length is : 25' /3.28 = 7.62 Mtr
Width is : 30' /3.28 = 9.14 Mtr
Depth is : 0.6"/3.28 = 0.15 2Mtr
Answer Posted / khadar babu
TOTAL VOLUME:
7.62*9.14*.15=10.44cum
(M15 concrete)
cement required= 10.44*6.48=67.7bags=3384.84Kgs
Sand required= 10.44*0.434=4.54cum
Aggregates required= 10.44*0.868=9.06cum
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
mean of NH4 pipe
What is difference between code and standard and specification?
What sizes of stones chips are used for foundation, column and floor casting. Please answer in detail.
Define What is the distance between railway tracks?
How will you Engage Labours on Site?
In the present situation of ban on mining sand from rivers,can we go for formation of earth dam filters viz;Horizantal sand blanket,inclined chimney and filters under rivetment with crushed rock sand of 6mm down size.If so what are the specifications and is there any codal provision for its authentication?
What is the difference between engineering stress and true stress?
how to calculate steel for slab or footings?
Differentiate orthographic and isometric projections?
What is the Tor steel Consumption for residential building G+24 footing (thum rule) ?
how we calculate the grade of the Bituminous materials.?????
why is M25 and Fe 500 assumed to be most economical? i feel it is not.This is because higher grade of concrete and steel has higher lapping length and anchorage length compared to lower grades..
hoe much fine & sourse agregate required for concrete mix of 1: 1.5:3 by volume in Cu.Ft
How to Know that veriation acceptable in CPWD Work Of 1:6 Cement Mortor Received Lab test report.
What are the different types of foundation?