Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how to find number of 16mm bar reqired for 5m length with 125 mm spacing ?

Answer Posted / lalit kumar

Number of bars = {(length in which the bar needed to be provided - 2(side cover))/ c to c spacing in b/w bars} + 1
No.of bars= {(5.0 - 2 X. 0.04)/0.125} + 1
No of bars= 40.36 or say 41 bars

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to calculate ventonite bag in pile ( pile depth 25 m dia 1m)

1957


How to calculate the cement consumption in RR Masonry in CM 1:8 for the foundation of Ground Level Reservoir

1613


yasser arfatcompleted his degree in civil from which university

2322


Calculate the maximum allowable speed on a horizontal curve of radius 350m if the maximum allowable values of the lateral coefficient of friction are 0.14 and the rate of superelevation is 0.08.

2584


how to caluclate sienerge qty in construction in ap

2452


HOW MANY BAGS OF CEMEMT USED IN PER M2 OF PARTITION WALL

1503


What will be weight of 0.5mm GI sheet per sq.ft?

17663


B.M DIAGRAMS & S.F DIAGRAMS OF CONTINOUS BEAMS

3015


WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)

3765


1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.

2173


what should be the PCC ratio to construct a plinth of (40x40x4)ft...??also its estimated cost??

3157


During reclamation how can the occurrence of mud waves can be rectified?

1354


a) Difference between Ghol , Chimney & fly ash bricks b)Floor to floor height is 3m , rise=15cm , tread 20 cm , how to design staircase means steps landing

3311


strength vs shape factor

2609


Explain the benefits of using standard terminology in the measurement process?(Tendering and estimation)

5106