how to calculate 1:2:4 ratio concrete cement, sand, metal
and water please give me brief calculation
Answer Posted / buhari adam nuhu kaakamu
NOTE:
1 CuM of concrete
Avg. final mix (Decnce) (AFM) = 1.52
Total proportion (TP) 1+2+4 = 7
Unit weight of cement =1440 KG/CuM
Solution.
Cement quantity required = AFM/TP
= 1.52/7
= 0.217 CuM
Cement is measure by weight
So therefore you multiply 0.217 by unit weight of cement
Cement quantity = 0.217 * 1440 = 312.48 KG.
Number of Cement bags = 312.48 / 50
= 6.2496 bags
Sand quantity = TP * 2
= 0.217 * 2
= 0.434 CuM
Stone quantity = TP * 4
= 0.217 * 4
= 0.868 CuM
Quantity of materials
Cement Bags = 6.2496 Bags
Sand = 0.434 CuM
Stone = 0.868 CuM
Is This Answer Correct ? | 11 Yes | 0 No |
Post New Answer View All Answers
What is passive earth pressure ?
If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?
what is conventional shuttering rate per square feet of built up area? what is Mivan shuttering rate per square feet of built up area? what is coupler shuttering rate per square feet of built up area?
What is Rankine Cycle?
. Write a C program to perform following functions:- a. Declare one integer variable of all the storage classes. b. Print all the variables without assigning any values in tabular format. a. The tabular format must contain the variable name, type, storage class and printed value on the screen in RED color.
What is the cost difference between site mix and ready mix concrete per cubic meter
What is the meaning of soil reinforcement?
flow of fluid takes place viscosity compressibilityu surface tension deformation under shear force
within an emergency scenario what are the safe systems of work a coss can setup as part of is duties
estimate quanitity of bricks(19x9x9cm without mortar), cement & sand in 10feet X 10feet wall ?
What are the different types of civil engineering?
How reactor of SBR installed , is it be over ground, fully under ground or semi sunk ?
How to do base isolation for RC framed structure using ETABS software?
how to take the quantity of block work and plastering 1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate
if mineral admixture add into concrete then what is the differences between full cement concrete & fly ash added concrete of their SP. Gr.?and for the changes of SP. Gr. what is the changes in concrete