Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

all rod lapping formula

Answer Posted / deoghar

Total Length is : 50.00mtr
Cutting length : 6.00mtr 
Dia of Bar : 32mm

Then no of lap is is

50.00-6.00=46.00mtr

46.00/4.400 ( 4.4000 is length of bar without development length)

= 10.450+1 = 11.450nos

Say 11 nos laps

Is This Answer Correct ?    1 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the cost of shuttering per Sqm.? How it is calculate by thumb rule...?

1967


Providing and casting in situ cement concrete M-25 of trap/granite/quartzite/gneiss metal for rcc, Providing formwork,Curing the concrete and Complete. what is rate per Cum. and what is rate for M-30 Grade Concrete.

3478


What are the different theories of failure under static load?

1295


Where can I get a Text Book on Design of Blast Resistant Buildings in PDF form.

1917


dialation means

2437


Need help in designing a degasser tower for 2m3/hr DM plant, also send me the formulae used

4845


What is min thickness,min grade of conc & age of PQC ?

9395


What are the responsibilities of a site manager?

1125


If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done.

2381


What are the main reasons for conducting pull-out tests for soil nails?

1234


how to calculate load for a bungalow and 1column carry how much load if the size of column ,9"*15" .....or total structure load......

1861


I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations

1483


material used for mendrel use to bend epoxy coated rebar

2159


"how can we find the approximate quantity of materials using in a building or total Expenditure in percentage for rough estimate after known the construction area(sqm)".please if you know something about that please post the answer.

2063


I have an plot with area 35*47 = 182.77 sq yards. Out of this iam planning to construct house with 1350 sqfeet each floor .iwanted to build a G+2 house.Need cost estimation for each item

1923