Can you explain about actual GI (gods issue) date and
planned GI date? Can actual GI date differ from planned GI
date?
Answer Posted / deepak chaudhur
Planned PGI date is depend on requested Delivery date and
Actual PGI date is depend on shipping point and Route
eg.
Material availability date is 17.10.2014
In Route PP days of 7(working days only) is being added now as default from Route XXXXXX to the MAD to determine the Goods Issue date of 28.10.2014 (17.10.2014+7 working days)
Transit days of 1 is being added to the Goods Issue date to determine the delivery date of 29.10.2014 (28.10.2014+1)
TLT days of 1 is being subtracted from the Goods Issue date to determine the Transport.plan.date of 27.10.2014(28.10.2014-1)
| Is This Answer Correct ? | 0 Yes | 2 No |
Post New Answer View All Answers
When you create a credit memo request do you always have to refer to a sales order or any other previous document?
Explain how the system can automatically determine the item category in the sales order.
Hi , I am 38 Yrs old and having 10 years of experience in trading industries like Computer hardware,software and steels and education field .I am having some exp of working in SAP as core team also. i want to know is there any limitations of AGE in SAP .
what are the organizational elements required for the sd transactions
Hi my name is subharajyoti and i have 6 yrs of exp in technical sale and at present doing sd module trainig in bangalore, i am looking for exp in real time projects, pls help me out
In a material master what is the base unit?
which are the roadmaps delevered by SAP solution manager I am going to take certification exam soon plz ans
What are the responsibilities of a technical consultant in an implementation project?
The whse had to go to manual mode and we have been left with deliveries that were not created. Is VL10H the tcode I would use to upload data from an excel or text file to create the deliveries in mass? If so, what are the steps to follow? Thank you!
What is the 'storage location rule'?
Can you share master data between several sales areas?
What is an mrp type?
How higher level item category is controlled?
Explain what copy control is and when copy control transition can be done? In what manner copy control transition can be done?
Do I have to change the update rules/source fields for the infostructure?