how many no of light weight solid blocks of size 600x200x200mm
required for 1cum of block work
Answer Posted / amit
first of all mortar quantity has to be calculated.
it comes b/w 15% to 17.5% of total block work.that means 0.15 cubicmeter to 0.175cum.therefore
Actual quantity of Blocks required=1-0.15=0.85cum
hence Nos of blocks=0.85/(0.6x0.2x0.2)=36 blocks
2 to 3% wastege= 1 blocks
thus total quantity=36+1=37 blocks
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
How much quantity of cement,sand,stone used to build 1 cum of cc road??
Floor to floor high of domestic building is 3m design a quarter turn staircase starting assume taken give a suitable diagram of it?
how do we calculate quantity of cement sand and aggregates in 1m3 of m20 m25 grade concrete?
Can we weld hot rolled steel ASTM A615 ? Please Give the detail answer please thanks alot
do you think we shall remove un wanted soil for foundation excavation even if the thickness of the soil strata is more than 8m ?
Gave a cantilever beam with 3 legs.Told to draw the bending moment diagrams, axial force diagrams and shear force diagrams.From BMD he asked to show how the reinforcement will be provided on the tension side.
how do you stabilize a waterlogged area in road construction
GIVE US DETAIL OF YOUR PRESENT EMPLOYMENT STATUS?
what is the venturi effect in buildings? what is green house concept?different types of dams? which dam is economical arch dam or gravity dam. what are the conditions favourible to both of them?
How to calculate the force on a column of three story building. What should be the base concrete height?.
material required for construction of 1cu.mtr wall (Cement, No of bricks (Brick size 40cm x 20cm x 10cm),sand,Quantity of water
please briefly explain calculating or estimating steel quantity for a RCC column?
how many sqft or cft of work done by a mason per day in all works such as brick,block,concrete,shuttering carpenter,reinforcement fabricator,painter,door window carpenter.....everything thank you
Whats the standard thickness of 20'/30' wide rcc service road and what will be the estimated cost per cubit feet
sir when can we expect the AEE results and when will be the interviews sheduled please guide us in this regard thanking you