what is relation between planned delivery and GR processing time .
Answer Posted / pratap barik
Planned delivery means Number of calendar days needed to obtain the material and GR Processing time means Number of workdays required after receiving the material for inspection and placement into storage.
| Is This Answer Correct ? | 6 Yes | 0 No |
Post New Answer View All Answers
How you can create consignment stocks?
What are the different sections in vendor master data?
Can you manually create purchase requisition with reference to documents such as purchase order or scheduling agreement?
Suppose you purchase new air filters and return the old damaged filters. This is a case of purchase and return simultaneously. How will you map such business scenario in sap mm?
what are the types of special stock available?
What is the differences between release procedure with classification and release procedure without classification? In which business scenario we use them?
Why is sap so popular? What are some of the other erp applications available in the market?
What are the possible values for 'procurement types'?
How are free items managed in a po? You need to tick the tem as free in the po. The price will be zero for such po's.
Why do we use document types in sap?
What is the use of ‘material status’?
What is 'goods movement'?
What is the organizational structure in the materials management (mm) module?
How to handle free items in po?
What is the organizational structure in the mm module?