How to calculate the no of bags required for 12mm thick 1:6
plastering?
Answer Posted / goutam giri
Considering 100 sqm plaster.
Wet Volume of plaster =100X0.012 =1.2 cum.
Add @ 20 % for filling the depressions, joints, wastage, etc.=0.24 cum.
Total=1.44 cum.
For dry volume of mortar increased by ⅓ of volume =0.48 cum.
Total dry volume of mortar =1.92 cum
Volume of cement:-1.92/7 = 0.2742/0.0347 =7.9 bag
Volume of sand:-0.2742*6 = 1.6452 cum
| Is This Answer Correct ? | 32 Yes | 4 No |
Post New Answer View All Answers
what are the duties of Site Engineer in work site?
What is change order request?
How to calculate the load of partion in flat slab if we use brick?
Design an underground tank of internal dimensions 6m x 3m x 3m. The soil surrounding the tank always remains dry. The tank shall be provided with a roof slab. The soil weighs 16000 N/m3 having an angle of repose of 30.
Who name us Engineer & Why?
do you think we shall remove un wanted soil for foundation excavation even if the thickness of the soil strata is more than 8m ?
what is meant by sustainable developement as far construction field is considered. Give suitable examples to explain the same
How to find out kg per Sft ?
how to calcualate the amount of stone,cement,sand required for 1cum of 450mm thick ruble stond masonary with ratio1:5, please me an answer with dtailed step
What is labor and material payment bond?
Define absolute co-ordinates?
Define polar co ordinates.
please give me the rates of RCC(CUM), PCC(CUM), Brick Work(CUM), Tile Flooring, Saria Shuttering
what radial pressure, the NP2 class rcc pipe can sustain?
what is the method used for marking of cantilevers in hirise buildings by using theodolite