Distinguish between neutral earthing and equipment earthing?
Answer Posted / dhananjay kumar from japla (gp
The star point of an electrical machine is earth to make the neutral point and ground
potential is called neutral earthing.
This is done so that a number of measurement and protective system
can be suitably connected with the power system.
The equipment earthing is done to protect operating personal to protect them for electrical shok.
In some cases equipment earthing also protect the environment from earthing. .......
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
What is the formula for selecting the cabels according to load? How to calculate what sq.mm cabel to be used?
If the earth is a good conductor of electricity, why don't people get shocked every time they walking on earth?
Is it possible to use a S1 duty class motor for crane application (S4)? If not, why?
what is the significance of cabability curve of alternator
i installed 100kva ups. what KVA genset they should provid in input side? plz any update formula or ans with reason.
how can service sitting be setted for MCCB?Example for sittings IR (CURRENT RATING),IS(CURRENT STARTING)IO (current operating)?
what is mean by descripiency relay? & wht is its ansi code?
HAI SENT HPCL APTITUDE QUESTION PAPER, MY EMAIL ID IS angus_eee04@rediffmail.com,angus_eee04@yahoo.com
Draw a circuit diagram in which if button is open we can use socket and bulb as a series test circit and if button is close than simple we can use socket as any load purpose.
Is there any Electrical supervisor license which gives permit to work whole India rather than individual state??
How will you justify IR value and Charging voltage of any motor,transformer and Cables.......???? . . . . . . . . Plz tell me any body Baljeet Singh, engineer_89@refiff.com
I have 4 DG set with 1500KVA rating. system breakers are 11KV & alternator are 415 Volts. Between alternator & breaker one stepup transformer used. i want to Know what is max. resistance for body earthing & 415 & 11KV V Neuteal earthing. my fault current is 14 times for 2 sec.
we have two motors 1250kW,6.6kV to be coupled on the same shaft ,so please provide assistance for their synchronisation.
in HT service 3ph 4 wire service Y-phase voltage shows zero . whether it is meter fault? or what be the reason ? if y-ph voltage zero ,can current is recorded? reasons for failure?
how many Classification of fire extinguisher