why the undervoltage relay's interlock is used in
earthswitch closing operation of the 400kV line scheme?









Answer Posted / nur.asidik

to make sure ES can be closed only if line is dead, besides that in common practice, CB status is needed also as interlock Earthing switch

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what are the dimensions for 200 kva transformer plinth (plateform),in which pcc m20 is used..

10783


what is the terminal voltage of dc series generator running at rated speed at no load?

6433


Define phase lag and phase lead?

647


I am getting above 60 V as open delta voltage against single phase unit ICT at tertiary delta formed and ICT getting trippped on NDR. ICT tested and found in order. PTs provided on tertiary are tested and in order. what may be the reason?

1504


What is inrush current?

645






What is meant by full pitched winding?

643


what is a power factor?

1325


raleigh method

1651


what is DRP panels?

1686


R=*ΒΆ l/a

1172


We are preparing another project which involves Waste heat recovery from a 1 MW GE Engine. The Engine in particular gives out flue gas at 487Deg C with a flow rate of 5650 kg/hour and this can be cooled to 180 Deg C. This gives a thermal output of ~ 594 KW that is available for input to VAM via heat exchanger / boiler. Additionally 581 KW will be available from engine jacket water (temperature profile 80/ 80 Deg C and a flow rate of 50m3/hr) Our estimation is that 300 TR of cooling is possible with a suitable VAM machine(s). Please advise what is the most suitable arrangement with maximum TR and min Capital expenditure. plz reply me as early as possible

1504


what do you mean by class PS CT and what are technical details needed for calculating it?

1523


how indusrial diesel generator work

1473


what is formula to cal cute earth pit numbers and size of earth strip used in earthing?

1802


Define average demand?

911