How to calculate the Qty of Mortar in 1 m3 Brick work? Detailed Calculation Required?
Answer Posted / santosh singh
quantity of dry cement mortar per cum = 0.35 m3
half brickwork per 100 sqm = 0.315 m3
| Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
how to calculate number of bitumen for road asphalt
What is chemical composion test
What is rate for brick masonry work of 1.0 m3 in cm 1:6?
at which depth the construction of tunnel is economical from cost and engineering aspect.
Which IS Code/American Code applied for coupler test of steel
A roof has a U value = 0.65 W/m2 .C. Extra insulation is to be provided. This insulation has a thermal resistance = 1.5 m2"C/W. Calculate the new improved U value.
How can we calculate 8- storied Madrasha Building pile capacity by taking SPT value at site?
in staad pro. modelling for a parallel scissors chord truss, when i assigned roller support i.e fixwd but with all Fx, FZ, Mx, My and Mz release except Fy... the analysis results " in stability at a joint, with direction Mx or My..what could be the reason...anyone please explaing
hoe much fine & sourse agregate required for concrete mix of 1: 1.5:3 by volume in Cu.Ft
Please send me the qunty. of mason/labour required in each day for different type of civil construction work?please send me ans. in my mail.my mail id is (parthamitra086@gmail.com) or here.
What is the strength of 1:6:12 mix?
How will you reduce the concrete flow after mixing the concrete
I want to know the material required per square foot in rcc roof. i.e. steel: kg/foot, cement/foot etc.
What is braced excavation all about?
what do you mean by yeild stress of a material? What will happen when hit is given to cement?