how many stones require for rr masonery work 1cum.
Answer Posted / santosh singh
For random rubble masonry work
1.25 cu m of stone is required per 1 cu m work
| Is This Answer Correct ? | 24 Yes | 2 No |
Post New Answer View All Answers
HOE TO YOU PLAN TO ACCHIEVE THE GOALS?
Test procedure of fly ash bricks as per code ?
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
Formula of area of crane hook
silt%= silt volume/ silt+sand volume is this right?
is there any thumb rule for calculating construction cost of the building with pile foundation per sft. area?
afe or not
1. What is coefficient use for calculation of shuttering. 2. What is coefficient use for calculation of reinforcement in one cum of concrete.
States some of the tool bars used in cad?
we have a bore well 275 depth & water is deliver at distance of 1000 feet from the borewell here iam not include the distance of depth and the deliver water horizontally at our reserviour tank on ground level
WHAT IS THE MAIN DIFFERENCE B/W HIGHWAYS AND MOTERWAYS?
How to calculate Volume of Wet cement concrete for a specific grade?
Explain moment of inertia and its importance.
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh
How to design 12*12*14 room having rrc slab ,coloum, beam,foundation?