how many stones require for rr masonery work 1cum.
Answer Posted / santosh singh
For random rubble masonry work
1.25 cu m of stone is required per 1 cu m work
| Is This Answer Correct ? | 24 Yes | 2 No |
Post New Answer View All Answers
Please tell me any one, how many quantity concrete paver block fixing perday ( 8hours) per mason??
for Precast foundation howmany days required we can shift the foundation with american Standards i need reference with section any body can help
how i get all type of short type question answer about civil engg
how much percent are used 20mm,10mm?
detailed calculation of the amount of cement used?
What are the main reasons for conducting pull-out tests for soil nails?
what is the coefficient for running feet to cft coversion both area and price
what is total volume of ingredients used in concrete accordingly
Define Workability ?
pls tell me , what is the water content
1:4:8 pcc calculation 591 cu.ft
what is detail procedure of eccentric footing? plz. give solved exmple?
Can anybody help by describing each and every step in short, used while giving a building layout by total station? Regards
what will be price of 1:2:4pcc per kg?
What expenses counted in contingencies and how much it is in related to built-up area of the building.